Kyiv Cluster Plants
Kyiv Region's First Sustainable Waste Management Cluster
A partnership transforming waste into energy and opportunity

50.1%
of the company's shares belong to three communities (Boryspil, Fastiv and Brovary)
49.9%
of the company's shares belong to REM & Co Sp Z.o.o
€302.6/ton Capital expenditure or capital expense (CAPEX)
26,000 tons of fresh organic waste/year

2 Plants: Um1 & Um2
Total productivity of the two plants:
480,000 tons of MSW/year
Total investment:
€145,255,000
€145,255,000
Planned Kyiv
Cluster Plants
Overview: Transforming Waste Management into Renewable Energy
The Kyiv Cluster includes two state-of-the-art waste processing facilities, strategically designed to handle municipal solid waste (MSW) and generate renewable energy. Construction is set to begin in September 2025, aiming for completion within 27 months.
All preparatory work and design are funded exclusively by the investor.
Um 2: Boryspil Plant – 360,000 Tons/Year
Core Features:
- Advanced Waste Sorting.
- Production of Synthesis Gas.
- Thermal Power Plant (TPP): 24 MW powered by synthesis gas.
- Rooftop Solar Station: 1.5 MW.
- Energy Storage Systems: 16 MW capacity.
Team Size:
- Up to 445 employees.
Budget:
- Estimated at €102,450,000.
Um 1: Fastiv Plant – 120,000 Tons/Year
Core Features:
- Advanced Waste Sorting.
- Production of Synthesis Gas.
- Gas-Piston Engines: 8 MW powered by synthesis gas.
- Rooftop Solar Station: 1.5 MW.
- Energy Storage Systems: 16 MW capacity.
Team Size:
- Up to 115 employees.
Budget:
- Estimated at €42,805,000.
Project Timeline
Start of Design Work: Spring 2024
Completion of Design Stage (Phase P) & Building Permit: August 2025.
Construction Start Date: September 2025.
Construction Period: 27 months
Construction Period: 27 months
Financial Model
Total Investment: €145,000,000.
- 15% Self-Funded: €22,000,000.
- 85% Credit-Financed: €123,000,000.